Have very little information to go on but here is our advice:

Collection pipe work: Assuming that the pipe work relates to gravity collection sewers: Normally for sewers running part-full (not surcharged) DN 100 min slope 1:100 DN 150 min slope 1:150 DN 200 min slope 1:200

For pumping mains different criteria apply.

Roughness k=3 for untreated sewage irrespective of material as slime is developed such that flow does not see material of construction.

Wastewater treatment: The proposed retention times do not look like conventional design. For example typical design requirements fro primary settlement tanks would normally be based on a sewage retention time of 1.5 to 2 hours maximum with a surface loading of 30 to 45 m3/m2.d at max flow.

The treatment objectives seem to be removal of solids and perhaps some anaerobic treatment of the solids. This would seem to require a design such as septic tanks where solids settlement will occur and the settled solids will receive some anaerobic treatment before removal and disposal of solids. However, as no flow data are provided it is not possible to comment, as septic tanks may not be applicable to larger flows.

An alternative would be the provision of a pond system with perhaps and anaerobic pond providing solids removal and secondary/tertiary ponds treating the effluent from the anaerobic ponds such that the desired effluent quality can be achieved.

Both of these options could give rise to odours, although that from septic tanks can be readily contained. The use of ponds assumes that land is available for this form of treatment.

Regards,

Andy Paskins (via James Montgomery)

click to hide/show revision 2
No.2 Revision
Harriette Purchas gravatar image
RedR TSS

Have very little information to go on but here is our advice:

Collection pipe work: Assuming that the pipe work relates to gravity collection sewers: Normally for sewers running part-full (not surcharged) DN 100 min slope 1:100 DN 150 min slope 1:150 DN 200 min slope 1:200

For pumping mains different criteria apply.

Roughness k=3 for untreated sewage irrespective of material as slime is developed such that flow does not see material of construction.

Wastewater treatment: The proposed retention times do not look like conventional design. For example typical design requirements fro primary settlement tanks would normally be based on a sewage retention time of 1.5 to 2 hours maximum with a surface loading of 30 to 45 m3/m2.d at max flow.

The treatment objectives seem to be removal of solids and perhaps some anaerobic treatment of the solids. This would seem to require a design such as septic tanks where solids settlement will occur and the settled solids will receive some anaerobic treatment before removal and disposal of solids. However, as no flow data are provided it is not possible to comment, as septic tanks may not be applicable to larger flows.

An alternative would be the provision of a pond system with perhaps and an anaerobic pond providing solids removal and secondary/tertiary ponds treating the effluent from the anaerobic ponds such that the desired effluent quality can be achieved.

Both of these options could give rise to odours, although that from septic tanks can be readily contained. The use of ponds assumes that land is available for this form of treatment.

Regards,

Andy Paskins (via James Montgomery)

click to hide/show revision 3
No.3 Revision

Have very little information to go on but here is our advice:

Collection pipe work: Assuming that the pipe work relates to gravity collection sewers: Normally for sewers running part-full (not surcharged) DN 100 min slope 1:100 DN 150 min slope 1:150 DN 200 min slope 1:200

For pumping mains different criteria apply.

Roughness k=3 for untreated sewage irrespective of material as slime is developed such that flow does not see material of construction.

Wastewater treatment: The proposed retention times do not look like conventional design. For example typical design requirements fro primary settlement tanks would normally be based on a sewage retention time of 1.5 to 2 hours maximum with a surface loading of 30 to 45 m3/m2.d at max flow.

The treatment objectives seem to be removal of solids and perhaps some anaerobic treatment of the solids. This would seem to require a design such as septic tanks where solids settlement will occur and the settled solids will receive some anaerobic treatment before removal and disposal of solids. However, as no flow data are provided it is not possible to comment, as septic tanks may not be applicable to larger flows.

An alternative would be the provision of a pond system with perhaps an anaerobic pond providing solids removal and secondary/tertiary ponds treating the effluent from the anaerobic ponds such that the desired effluent quality can be achieved.

Both of these options could give rise to odours, although that from septic tanks can be readily contained. The use of ponds assumes that land is available for this form of treatment.

Regards,

Andy Paskins (via James Montgomery)